Complaint of the Allottees are maintainable in RERA even after the expiry of the registration period of a project under RERA.

M/S Imperia Structures Ltd. Vs. Anil Patni and another

Merely because the registration under the RERA Act is valid till 31.12.2020 does not mean that the entitlement of the concerned allottees to maintain an action stands deferred. It is relevant to note that even for the purposes of Section 18, the period has to be reckoned in terms of the agreement and not the registration. Therefore, the entitlement of the Complainants must be considered in the light of the terms of the Builder Buyer Agreements and was rightly dealt with by the Commission.

Cases where such proceedings under the Consumer protection Act are initiated after the provisions of the RERA Act came into force, there is nothing in the RERA Act which bars such initiation. The absence of bar under Section 79 to the initiation of proceedings before a fora which cannot be called a Civil Court and express saving under Section 88 of the RERA Act, make the position quite clear. Further, Section 18 itself specifies that the remedy under said Section is “without prejudice to any other remedy available”. Thus, the parliamentary intent is clear that a choice or discretion is given to the allottee whether he wishes to initiate appropriate proceedings under the CP Act or file an application under the RERA Act.

The Rules of the Bar Council of India do not permit advertisement or solicitation by advocates in any form or manner. This Blog and the contents hereof are merely for informational purposes and not in the nature of solicitation or an advertisement.

By entering this Blog in any manner, you confirm and acknowledge that you have voluntarily sought the information posted on the website.